EV Charger Installation Timeline: What to Expect

From initial enquiry to your first charge, here's a detailed breakdown of the EV charger installation process and how long each step takes.

By James Wilson·18 June 2024·5 min read·Updated 20 November 2024

Overview

Getting an EV charger installed typically takes 1-3 weeks from initial enquiry to completion. Here's what happens at each stage.

Week 1: Enquiry and Quote

The process begins when you request quotes from installers. Most installers respond within 24-48 hours. During this phase:

  • Day 1-2: Submit enquiry and receive initial response
  • Day 2-4: Photo survey or site visit to assess your property
  • Day 4-7: Receive detailed quote including charger, installation, and any additional work needed

Week 2: Booking and Preparation

Once you accept a quote:

  • Day 8-10: Confirm installation date and pay deposit (if required)
  • Day 10-12: Installer orders charger and materials
  • Day 12-14: DNO notification submitted (if required)

Installation Day

The actual installation typically takes 2-4 hours:

  • Hour 1: Final site assessment and preparation
  • Hour 2: Installing mounting bracket and running cable
  • Hour 3: Electrical connections at consumer unit
  • Hour 4: Testing, commissioning, and handover

After Installation

  • OZEV grant paperwork (if applicable)
  • Building regulations certificate
  • App setup and demonstration
  • Warranty registration
installationtimelineprocesswhat-to-expect